The Challenge of Funding Subway Renewal

At its November 22, 2023 meeting, the TTC Board will consider a report New Subway Train Procurement and Implications for Line 2 Modernization and Future Growth which goes into considerable detail on several related capital projects related to renewal of both Line 1 Yonge-University-Spadina and Line 2 Bloor-Danforth.

The TTC is in a very difficult position for capital planning because for many years it understated the size of the capital backlog and also tended to treat related projects, or even components of the same project, as separate items. This led to low-balled estimates of total costs and, in some cases, piecemeal execution of projects. Now that we see “all in” costs, the problems facing the system are perceived more seriously, but just at a point when new money to invest in existing subways is hard to find.

Although the TTC called for proposals for a replacement of the Line 2 fleet of T1 trains, with add-on provisions for system expansion, this was cancelled in June 2023 due to lack of funding commitments from either the Provincial or Federal governments.

The report proposes three scenarios depending on when new trains and facilities would be delivered and built at total costs ranging from $8.5 to $10 billion including inflation. Very little of this has committed funding.

This is not just a question of buying new trains, but of building, or renewing, many facilities:

  • Greenwood Carhouse dates back to the opening of the BD subway and needs to be modernized and rebuilt to handle a new fleet.
  • The signal system on Line 2 dates to the 1960s and must be replaced both to maintain reliability, improve operations and provide for service growth.
  • Additional trains for both Lines 1 and 2 will require more storage including a major new maintenance facility for Line 1.

The funding sought by this report does not include companion upgrades that have been flagged in the overall capital plan:

  • Running more frequent service requires more traction power on top of state of good repair work needed for both subway lines’ power systems.
  • More service means more passengers, and some key stations cannot handle additional demand between the platform and street without additional circulation capacity.

Moreover, there are major projects beyond subway fleet renewal that are either partly or totally unfunded even at the City level, never mind its partners:

  • Ongoing replacement of the bus fleet including electrification
  • Any provision for service growth to improve transit coverage and encourage a shift to transit riding especially in areas where it is not competitive with auto
  • LRT lines in the waterfront or Eglinton East
  • Platform screen doors to prevent access to track level

Even if the fleet and signal renewal for Line 2 finds much-needed financial support, this is only the beginning of the TTC’s search for capital, and I have not even mentioned the need for ongoing state of good repair.

In the short term, the TTC has been “saved” from a capacity crisis by the covid pandemic and the loss of subway riding. Only a few years ago, the concern was not empty trains, but platforms full of riders who could not move. Although the subway is not back at full demand, recovery is well underway. Here are historical figures and projections for the future from the report.

2041 might sound a long way off, but in the scheme of subway fleet planning, it is fairly near given both the lead time to buy new trains and their 30-year design life. What we plan for today will affect the system for decades to come.

This forecast will be updated with results from the current Transportation Tomorrow Survey and other planning work to provide an outlook to 2051.

These projections translate to service requirements on the two lines. Note that this is likely based on the historical ratio of peak to all day demand. Although work-from-home may shift some riding away from peaks especially on Mondays and Fridays, this would still leave the midweek days facing crowding. It would be dangerous to make plans for lesser demand as a short-term cost saving measure.

Line 1 has already been converted to Automatic Train Control (ATC) with moving block signalling that can handle more trains/hour. Note that the projected Line 1 service is at 36 trains/hour, or every 100 seconds. This will be challenging to sustain especially at busy stations and terminals.

The current signal system on Line 2 cannot support headways below about 140 seconds, the pre-pandemic peak service level on that route. This is equivalent to 25.7 trains/hour which gets us only to the 2032 projected requirement.

This translates into the following requirements for a larger fleet.

The 55-train replacement for Line 2 where there are now 61 trains is based on the capacity with new trains (similar to those now on Line 1) with about 10% more room than the old ones. This finally addresses the excess of T1 trains in the fleet ever since the TTC decided to run Lines 1 and 4 entirely with new “TR” trains and ATC, and relegated the T1 fleet to Line 2.

The Metrolinx options are for the Richmond Hill and Scarborough extensions. Growth trains are to permit the operation of more frequent service than the existing fleet can support.

Note that Line 4 Sheppard is not included here as it has a dedicated set of six 4-car trains that can handle projected growth on that line. Depending on the extension of Line 4, a future procurement of trains and storage facilities could be required.

In the remainder of this article, I will describe the scenarios and implications of choices the TTC, Council and its funding partners will make in the near future.

Recommendations

The report recommends that:

  • The TTC prioritize funding in the capital budget for:
    • New subway cars and related projects with a cost of $3.2 billion as the City’s share.
    • A 30-year state of good repair overhaul of the T1 fleet.
    • Risk mitigation activities for Line 2 related to fleet and signal system life extension.
  • Subject to confirmation of funding, the CEO issue an RFP for new trains needed on the existing Line 2 with options for extensions and demand growth on the system.

This will have effects not just for subway planning but for other TTC capital project funding and timing.

Continue reading

TTC Board Meeting Preview: September 26, 2023

The TTC Board will meet at Scarborough Council Chambers at 10:00 am on September 26, 2023. This will be the first meeting of the reconstituted Board under Mayor Chow’s administration. Among the reports on the agenda are:

The agenda also includes a report Update on TTC’s Partnership Approach to Community Safety, Security and Well-Being on Public Transit. I will address this in a separate article.

Continue reading

TTC Board Meeting July 12, 2023

The TTC Board met on July 12 with a variety of items on their agenda. I have already addressed the presentation of pending service changes as well as a discussion of short turns in previous articles.

Topics discussed here include:

  • The CEO’s Report for July 2023
  • Elevator and Escalator Overhauls
  • Wheel-Trans Transformation 2023 Program Update
Continue reading

TTC Cancels RFP For New Subway Trains (Updated)

A Request for Proposals for new subway trains has been cancelled due to lack of funding. The following notice was sent to all vendors on Friday, June 23:

The Toronto Transit Commission issued a Request for Proposals (RFP) on October 13, 2022 for the procurement of New Subway Trains.

The RFP indicated that the TTC was in the process of actively pursuing additional funding from other orders of government (Provincial and Federal), and that contract award was subject to receiving full funding commitments by early 2023. As detailed in item 1.2.2 – Funding Status of Part 1 – Invitation and Submission Instructions of the RFP document: “Timelines associated with this RFP have been communicated to potential funding partners, and a request for confirmation of funding by early 2023 has been requested. In order to receive the NST deliveries in time for the legacy fleet replacement and to meet growth needs, the TTC has elected to commence the procurement at this time, however, contract award is subject to receiving full funding commitments.”

Unfortunately, the additional funding required has not been secured and as such, TTC is cancelling the RFP effective immediately, and the Bonfire Portal will be closed.

The TTC will continue to have discussions with the Provincial and Federal governments on funding requirements for New Subway Trains and evaluate the requirements for issuance of a future Request for Pre-Qualification and Request for Proposals in the future.

Where this leaves future projects for enhancement of Line 2 Bloor-Danforth, conversion to Automatic Train Control and provision of full service on the Scarborough Subway Extension is anyone’s guess.

This is a project which was initially delayed by CEO Rick Leary in favour of a fleet rebuild, then reactivated as his attitude to the worth of ATC warmed with the success of the Line 1 conversion, a project very much the work of his predecessor Andy Byford and his team. The focus on spending for new lines has left major state of good repair such as fleet renewal high and dry, and this RFP cancellation show where that shortsighted policy has brought us.

I have reached out to TTC Media Relations for comment. This post will be updated as more information becomes available.

Updated June 26, 2023 at 3:45 pm

The TTC replied to my query for comment with the following:

As the posting says (or should), the purchase of the cars is contingent on funding being secured.

That has not yet happened, although discussions are ongoing.

This was about being transparent with bidders and letting them know that once funding is secure, we would re-post.

It is worth noting that as recently as the TTC Board meeting of June 12, 2023, there was no mention in the public session that this action was imminent. Here are the relevant pages from the Major Projects Update.

Updated June 26, 2023 at 5:00 pm

How many trains will the Scarborough Subway Extension require?

The TTC owns 370 cars in the T1 fleet which operates Line 2. That is equivalent to 61 6-car trains plus four spare cars.

The scheduled AM peak round trip time on the existing Line 2 is 105 minutes. For the maximum service possible with the existing signal and train control system, one train every 140 seconds, requires 45 trains. That was the AM Peak scheduled service in January 2020 before the pandemic-related service cuts. One additional train was on standby as a “gap” train for a total of 46. Allowing for spares at 20%, this requires a fleet of about 55 trains leaving only 6 spare for expansion.

The Scarborough extension is only marginally longer than the Line 1 extension from Eglinton to Finch with similar station spacing. A one-way trip on that part of Line 1 takes about 12 minutes, or 24 for the round trip. By analogy, that would make the round trip on the extended Line 2 about 129 minutes, and would required 55 trains with nothing left over for extras. Including spares at 20% would require a fleet larger than the TTC now owns.

Alternately, if every second train short turns at Kennedy Station leaving a 280 second service (4’40”) to Sheppard East, the line could probably operate with 50 trains which just fits within what is available.

One might argue that with a new fleet and the benefits of Automatic Train Control, overall speed could be improved and with that the fleet needed for full service to Sheppard could be reduced. But that is moot if TTC maintains the existing fleet.

When the SSE was planned, it had a pocket track east of Kennedy Station, but this was cut to save money, then it was restored. I wonder if someone is counting trains, or just hedging their bets on service levels beyond the existing terminus?

In any event, a failure to buy new trains has the double effect that it will condemn Line 2 to manual operation with an aging signal system for the foreseeable future, and will prevent the operation of full service beyond Kennedy in peak periods unless the Bloor-Danforth line never returns to the pre-pandemic peak service level.

TTC Board Meeting April 13, 2023

The TTC Board will meet on April 13, and the agenda for their meeting is rather small. Notable by its absence is any reference to the service cuts planned for May 7, 2023.

The big items in the public portion of the agenda are the monthly CEO’s Report and an update on TTC’s finances and major capital projects to the end of 2022.

There are also two reports on collective agreements and non-union salaries. Although the details lie in confidential attachments, the public reports give an overview of the various labour contracts and salary drivers across the organization. I leave perusal of these to interested readers.

Finally there are a few references to the TTC’s eBus program scattered through reports. I will consolidate this info in its own section at the end of the article.

Correction April 18, 2023: It turns out that the size of the bus fleet shown in the graphic below is wrong. There are only 2041 buses, not 2114, in service as of March 2023. The article has been amended to reflect this.

Continue reading

TTC Issues RFP For New Subway Trains

On October 13, 2022, the TTC issued a Request for Proposals for a new fleet of subway trains. The submission deadline is July 28, 2023, and the anticipated contract award date is December 22, 2023.

This article is not an exhaustive review of the specification which is over 1,200 pages long, but an attempt to pick up major points including differences between the new fleet and the existing TR trains. The information has been organized for easy reading with related points grouped together, not necessarily the sequence in which they appear in the RFP.

Updated October 21, 2022 at 9:10 am:

  • A section has been added with information on car ventilation as it relates to health concerns and air quality.
  • A section has been added with more details of the emergency detrainment at the cab ends of the train.

Click here to jump to these updates.

The initial order would be for 480 cars (80 6-car trains) to replace the existing T1 fleet which operates on Line 2 Bloor-Danforth and to provide both for ridership growth and added trains for the Scarborough and Yonge North extensions. The delivery window is 2027-2033.

The trains are intended to be operated as much as possible like the existing TR fleet on Line 1 to minimize retraining requirements.

Although it is buried in an appendix, the TTC proposes a new exterior livery for the trains bringing the red from surface vehicles back into subway territory.

The requested design life for the cars is 35 years, somewhat longer than the 30 year span usually associated with a new fleet, but not unreasonable given the usual lag in replacement orders. For example, the T1 fleet of 370 cars was delivered between 1995 and 2001, and so the first of them will be 33 years old when the first new trains arrive.

Pre-pandemic service on Line 2 was provided at peak by 46 trains (January 2020 schedules). Allowing for spares at 20 per cent, this makes the peak requirement 55 trains compared to the present T1 fleet of 61 trains. (The extra T1s were displaced from Line 4 Sheppard when it converted to 4-car TR sets.)

The initial round of industry consultation took place in 2021 and resulted in pre-qualification of four potential suppliers:

  • Alstom Transport Canada Inc.
  • CRRC Qingdao Sifang Co., Ltd.
  • Hyundai Rotem Company
  • Kawasaki Rail Car, Inc

The next round of vendor consultations and proposals will only occur with these four companies.

A key issue here is funding. The RFP states:

The TTC has secured commitment to date of $624 million from the municipal government and is actively pursuing additional funding from the other orders of government (Provincial and Federal) towards the full estimated cost of the project. Timelines associated with this RFP have been communicated to potential funding partners, and a request for confirmation of funding by early 2023 has been requested. In order to receive the NST [“New Subway Train”] deliveries in time for the legacy fleet replacement and to meet growth needs, the TTC has elected to commence the procurement at this time, however, contract award is subject to receiving full funding commitments.

TTC RFP, Page 4, Section 1.2.2

There is a 25 per cent Canadian content requirement in the RFP.

There is an ironic leftover in the specification that the trains should be capable of operation on existing lines, new extensions and a new “Relief Line”. This spec has been around for a while. [Technical Specification section 1.1.1]

In past financial plans, TTC management warned about due dates for funding needed to acquire trains in a timeframe that would fit with earlier proposals for a Line 2 Renewal project. That timeline has now passed, and it is clear that delivery of the new fleet might not be completed in time for the Scarborough and Yonge North proposed opening dates in 2030. This could leave more of the old T1 fleet in operation until enough trains are available to provide full service on extended Lines 1 and 2. That, in turn, has implications for the full transition to ATC signalling on Line 2.

It is possible that the total train requirement will be reduced from pre-pandemic levels by operation of both lines at a higher average speed taking advantage of Automatic Train Control and of the “high rate” available but not used. However, that option comes with caveats about the timing of ATC installation on Line 2 as well as the effect of higher speeds on track maintenance and power consumption.

The proposed delivery schedule is shown in the table below. The first two trains are planned for 2027 to allow acceptance testing and tweaking of the specification should problems arise before the main production run. Cars will be delivered to Wilson Carhouse by flatbed truck.

The 32 optional trains are allocated as below:

  • 7 for the new Scarborough Subway Extension
  • 8 for the new Yonge North Extension
  • 5 for the headway improvement on Line 1
  • 8 for the maturity service on the new Yonge North Extension
  • 4 for the maturity service on the new Scarborough Subway Extension

Delivery schedule relative to Notice to Proceed:

  • 40 months: Availability of first train at Wilson Carhouse for testing and commissioning
  • 42 months: Availability of second train at Wilson Carhouse for testing and commissioning
  • 52 months: Trains 3 to 10
  • 60 months: Trains 11 to 20
  • 66 months: Trains 21 to 30
  • 72 months: Trains 31 to 40
  • 77 months: Trains 41 to 50
  • 81 months: Trains 51 to 60
  • 85 months: Trains 61 to 70
  • 89 months: Trains 71 to 80

Availability for service is one month later. To put it another way, when a train arrives, it is expected to work more or less “out of the box” without months of testing and fixes.

Continue reading

Will Line 2 Renewal Ever Happen?

Those of us who can remember back to days before the pandemic, when Andy Byford was the TTC’s CEO, will know that there were frequent questions at the TTC Board about upgrades to the Bloor-Danforth subway, Line 2. All of the focus seemed to be on the Yonge-University-Spadina Line 1 with new signalling, trains and the Vaughan extension.

Byford confirmed that work on a Line 2 plan was underway, but never presented one in public. However, it does not take a lot to work out what might have been in this plan.

  • Automatic Train Control (ATC) signalling to replace the 1960s-era technology still in use.
  • New trains to replace the existing fleet of T-1 trains that would reach their design life of 30 years in the late-2020s.
  • Additional trains for service increases possible with ATC as well as for the Scarborough extension.
  • Additional/new maintenance facilities for a larger Line 2 fleet, plus provision for the then-planned stabling of Relief Line trains at Greenwood Yard.
  • Storage and maintenance facilities for the growing fleet of subway work cars.
  • Potential integration of a western yard project with an extension of Line 2 beyond Kipling Station.

This plan requires a lot of funding that the TTC still does not have, action to launch procurement of long lead time rolling stock and infrastructure, and a level of project co-ordination for which the TTC is not particularly noted.

That co-ordination issue arises in part from the funding challenge, and the tendency politically to ask for only what is strictly needed for “today’s” work hoping that Santa Claus will arrive in time to fund the rest. This was a direct cause of technical problems with the Line 1 ATC project that was cobbled together over time. It started with a superficially simple desire to replace the then-existing 1950s signals on the original line from Eglinton to Union. The feeling was quite clear: the TTC Board and Council would never commit to a full ATC conversion project because it would be too expensive.

Unfortunately what resulted was a mixed bag of signalling technologies that were incompatible with each other. To rescue the project, Byford recommended ripping out some already-installed equipment so that the line could be standardized. A related decision was that the Vaughan extension would open with ATC in place rather than, as originally planned, a traditional block signal system that would have to be replaced as a separate project.

Continue reading

Toronto Contemplates Net Zero Plan

Updated January 13, 2022 at 6:45 am: Sundry typos and scrambled phrases have been corrected. The projection of additional bus requirements for a 70 per cent service increase has been corrected to include spares.

At its recent meeting, Toronto Council endorsed a plan to move the City to Net Zero emissions by 2040. A review of the full plan is well beyond the scope of this blog, but some proposals affecting transit service and operations are very aggressive.

If Toronto is going to be serious about this we need a detailed examination of assumptions, scenarios, cost projection, and plans out to 2040. Where will population and job growth be? How will transit serve them?

Before I get into the report itself, a quotation from former TTC CEO Andy Byford is worth mention.

Andy Byford sums up the role of a transit system:

“…service that is frequent, that is clean, that goes where people want to go, when people want to go there, that is customer responsive, that is reliable, in other words that gets the basics right …”

Andy Byford on CBC Sunday, December 21, 2021

Too often we concentrate on big construction projects, or a new technology, or a showcase trial on one or two routes rather than looking at the overall system. In particular, we rarely consider what transit is from a rider’s point of view. It is pointless to talk about attracting people to use transit more if we do not first address the question of why they are not already riding transit today. This is an absolutely essential part of any Net Zero strategy.

The reports contain a lot of material, although there is some duplication between them. They contain proposals for short and medium term actions. At this point, Council has not embraced anything beyond the short term plan.

From a transit point of view, that “plan” is more or less “business as usual” and does little to challenge the current status of transit service in the short term. There is hope that electrification of the diesel/hybrid bus fleet might be accelerated, but little sense of what, on a system-wide basis, would shift auto users to transit beyond works already in progress.

A vital point here is that transit has two major ways to affect Council’s Net Zero goals:

  • Conversion of transit vehicles to all-electric operation will reduce or eliminate emissions associated with these vehicles, depending on the degree to which the electricity sources are themselves “clean”. This is a relatively small part of the City’s total emissions.
  • Shifting trips from autos to transit (or to walking or cycling) both reduces emissions and relieves the effects of road congestion, including, possibly, making more dedicated road space available for transit and cycling. Emissions from cars are much more substantial than those from transit.

In the short term, the overwhelming focus is on conversion of the existing bus fleet to electric operation, not of expanding service to attract more riders. Improvements to specific routes might come through various transit priority schemes, but these will not be seen system-wide. Based on demand projections, large scale capital works, notably new subway lines, will primarily benefit existing riders rather than shifting auto users to transit.

The short term targets related to transit are quite simple:

  • Electrify 20 percent of the bus fleet by 2025-26.
    • This effectively requires that 400 diesel or hybrid buses be converted. The TTC already plans to buy 300 eBuses, and the Board has asked TTC management to look at accelerating this conversion. This target is very low hanging fruit provided that someone will pay for the buses.
  • Further targets are 50 per cent conversion by 2030, and 100 per cent by 2040.
    • Looking at the TTC’s likely replacement schedule (discussed in my Capital Budget Follow-Up), they will easily be achieved as much of the existing fleet is due for replacement by the early 2030s. Hybrid buses to be acquired this year will reach end of life in 2034-35.

This is an endorsement of “more of the same” in our transit planning, but no real commitment to making transit fundamentally better so that it can handle many more trips at lower emission rates than today.

Looking further out there are proposals for substantially more transit service and free fares, but these are not fully reflected in projected costs or infrastructure needs.

Some of the proposals for the NZ2050 plan are, shall we say, poorly thought-out:

  • Convert one lane of traffic to exclusive bus lanes on all arterials.
    • Many arterials are only four lanes wide and taking a permanent bus lane has considerable effects on how the road would operate. This is a particular problem for routes with infrequent service during some periods of operation.
  • Increase service frequency on all transit routes: bus by 70%, streetcar by 50%, subway off-peak service increased to every 3 mins.
    • This represents a very large increase in transit service with effects on fleet size, facilities and, of course, budgets. This would require an increase in the bus and streetcar fleets beyond what is already planned as well as construction of new garages and a carhouse.
  • Tolls of $0.66/km on all arterial roads.
    • This would apply only to fossil-fueled cars, and the forecast amount of revenue is less than half of the additional funding transit would require.
  • No transit fares.
    • The immediate cost of this would be about $1.2 billion in foregone fare revenue, offset by about ten percent in the elimination of fare collection and enforcement costs.
  • Shift 75% of car and transit trips under 5km to bikes or e-bikes by 2040.
    • This is truly bizarre. In effect, transit stops performing a local service for most rides and they are shifted to cycling. The average length of a transit trip is under 10km, and many are shorter. Moreover, trips are often comprised of multiple hops each of which might be quite small. There is a small question of how much uptake there would be in poor weather conditions.
  • Shift 75% of trips under 2km to walking by 2040.
    • Even some transit trips are short, and transit, especially with improved service, is the natural place for these trips. It is not clear whether the plan would be to somehow deter transit users from making very short trips just as, indeed, a car driver would.

[Revenue and cost issues are discussed in more detail later in this article.]

With all of the planned investment, transit’s mode share of travel is projected to fall, while walking and cycling would rise considerably in part because of the policy of diverting short trips. It simply does not make sense to push people off of transit just at the point where we are trying to encourage transit use. This part of the plan is laughably incoherent, and is an example of how good intentions can be undermined by poorly crafted policy.

For example, it is less than 5km from Liberty Village to Yonge Street, and if we were to take the proposal seriously, we would expect most people to cycle to work downtown, not take GO or the streetcar services. I look forward to the public meeting where this scheme is unveiled to the residents. If the demand for GO and for the King car is any indication, they do not want to use “active transportation”. Similarly, the planned development at East Harbour is less than 5km from downtown.

Meanwhile, transit electrification itself only eliminates 3 per cent of existing emissions, assuming a clean source of electricity. The subway and streetcar systems already are electrified, and both have capacity for growing demand if only more service were operated.

Reports:

The Council motion reads, in part:

City Council endorse the targets and actions outlined in Attachment B to the report (December 2, 2021) from the Interim Director, Environment and Energy, titled “TransformTO Net Zero Strategy”.

Councillor Layton moved two amendments:

* Request the Board of the Toronto Transit Commission to identify opportunities to accelerate the Green Bus Program and to request the CEO, Toronto Transit Commission to report to the Board in the second quarter of 2022 on these opportunities.

* City Council request the City Manager, in consultation with the General Manager of the Toronto Transit Commission, to outline in the 2022 Budget proposal options to increase spending on surface vehicles and hiring additional operators aimed at increasing ridership to get us on the path to achieving the TransformTO goals.

The first amendment echoes a request from the TTC Board to its management at the December 20, 2021 meeting. Acceleration of eBus purchases will require additional funding from somewhere, as well as a vendor capable of meeting a larger order. It will also have effects on TTC infrastructure needs for garaging.

The second amendment is more pressing because it speaks to the 2022 Budget process that will launch on January 13. If the TTC is going to ramp up service this year, this must be factored into the budget. A likely problem will be that any growth beyond that now planned will be entirely on the City’s dime rather than supported by other governments. However, we need to understand what could be done, if only to know the cost should a “fairy godmother” show up with some spare change.

Neither the amendment nor the short-term target for 2022-2025 gives any indication of just what is meant by “better” transit service, nor do they distinguish between restoring pre-covid service levels and going beyond that to encourage more ridership.

The points listed above for NZ2050 are excerpted from Attachment C, the technical background report. A casual reader might think that Council has embraced a very expansive view of transit’s role, but they have not.

The tactics from Attachment C are notably absent from Attachment B which refers to them, but actually lists a much more restricted set of transit goals. I have confirmed with City staff that Council has only endorsed Attachment B.

Q: For clarification: There are, broadly speaking, two levels of a shift in the emphasis on transit in the short term plan to 2030 and in the longer term to 2040 and beyond. Reading the Council motion, it appears that Council has endorsed the short term plan (Appendix B), but has not endorsed the more aggressive targets of the longer term set out in Appendix C. Is this a correct interpretation?

A: Yes. City Council endorsed the targets and the actions outlined in Attachment B ‘TransformTO Net Zero Strategy’. Attachment C is a technical backgrounder report that was used to inform the targets and actions that were recommended and adopted.

Email from Steve Munro to Toronto Media Relations, December 29, 2021. Response from Toronto Environment & Energy Division, January 10, 2022.

That is a polite way of saying “we had some really aggressive ideas, but we know enough not to bring them to Council”.

“Transit” vs “Transition”

In the process of reviewing the reports, I searched on the word “transit”, but got hits more frequently on “transition” as there are many other sectors where reduction or elimination of emissions are possible and on a large scale.

According to the most recent greenhouse gas inventory, transportation is the second largest source of GHG emissions, accounting for 36 percent of total emissions with approximately 97 per cent of all transportation emissions originating from passenger cars, trucks, vans, and buses. Gasoline accounts for about 30 per cent of Toronto’s total GHG emissions.

TransformTO: Critical Steps for Net Zero by 2040. p. 30

Here is a pie chart showing the relative contribution of each proposed action in the Attachment C list which is a more aggressive set of changes than Council adopted. Note the small contribution of transit (red) compared with other areas such as personal and commercial vehicles and changes to building energy use.

Based on Section 7: Low-Carbon Actions pp 52-56 in the Net Zero Technical Report

Another way to look at this is shown in a chart of energy sources and emissions generated by each transportation sector as the full NZ plan is implemented.

  • Top left: the emissions of urban buses are shown in green. This falls off to zero as the bus fleet electrifies.
  • Middle left: the decline in diesel (green) is a combination of transit, trucking and a small contribution from diesel-powered autos.
  • Bottom left: Cars and light trucks are the overwhelming contributors of emissions within the transportation sector.
  • On the right, the charts are harder to accept at face value because they include the effect of a very large shift of short trips to active transportation. An interesting comparison would be what might happen if autos electrified, but did not lose mode share.

That last point has a knock-on effect because if short trips are not shifted, but are only electrified, they will contribute a substantial demand to generating and charging capacity, not to mention continued auto traffic and competition for road space.

Net Zero Technical Report, p. 91
Continue reading

TTC 2022 Capital Budget: Board Meeting Follow-Up

This article is a follow-up to the TTC Board’s discussion of their 2022 Capital Budget at the meeting of December 20, 2021.

Links of interest:

The topics here are a bit scattershot as was the Board debate, but they include:

  • The Toronto Net Zero 2040 plan and electric buses
  • The conflict between budget planning timeframes and available funding
  • The growing backlog in State of Good Repair
  • Fleet replacement timing issues
  • Where the money comes from
  • The need to co-ordinate related projects within the budget
  • Funding for capital programs
  • Future subway demand and capacity enhancements

There is always a problem with the complexity of the budget that drops on Board members at most a week before the meeting where it will be approved.

There is no “Budget Committee” at the TTC, and so there is no group within the Board who are primed for the debate and can vouch for management’s work in the same manner as the TTC’s Audit & Risk Management Committee. The Board used to have a Budget Committee, but it languished under an uninterested chair (ironically, a member of Council’s hawkish right) and the current Board is unwilling to recreate it.

This says a lot about how seriously (or not) they take their oversight role. Let a few pencils go missing and the Audit folks will be all over the problem, but billions in capital spending and the underlying policy decisions go with little review. This should be a job for whatever TTC Board is crafted for 2023 after the next municipal election.

For those interested in the details, read on.

Continue reading